Traffic Advice
Extension of Temporary Traffic Arrangements on Ching Hong Road, Tsing Yi
Motorists are advised that, to facilitate the footbridge construction works, the following temporary traffic arrangements will continue to be implemented from 1:30 a.m. to 5:00 a.m. daily on 1, 4, 12, 14, 15, 18, 20, 22, 25, 27 and 28 April and 3, 5, 10, 12 and 13 May 2023 on Ching Hong Road –
- Cheung Ching Bus Terminus and its ingress access road will be temporarily closed to all vehicular traffic.
(ii)
Banning of Turning Movement
- All vehicles will be temporarily prohibited from making right turn from Ching Hong Road northbound to Cheung Ching Bus Terminus.
(iii)
Temporary Traffic Arrangement
- The egress access road of Cheung Ching Bus Terminus will be converted from two-lane one-way traffic to two-lane two-way traffic, to facilitate vehicles on Ching Hong Road northbound heading for Cheung Ching Estate, Cheung Ching Estate Community Centre and Father Cucchiara Memorial School.
Appropriate traffic signs will be erected on site to guide motorists.