Members of the public are advised that in order to facilitate lift installation works, the following temporary traffic and transport arrangements will be implemented on Yat Ming Road, Fanling from 12.00 midnight to 5.00 am daily from 18 July 2025 to 1 August 2025:
(1) LANE CONVERSION
A section of Yat Ming Road westbound near Buddhist Ching Kok Lin Association School from a point about 65 metres east of its junction with the unnamed access road leading to King Shing Court to a point about 185 metres east of the same junction will be temporarily converted from two-lane two-way traffic into one-lane two-way traffic.
(2) PUBLIC TRANSPORT SERVICE ARRANGEMENTS
The bus stop on Yat Ming Road westbound near Buddhist Ching Kok Lin Association School will be temporarily relocated. Details are as follows:
|
Routes Nos. |
Direction |
Temporary Arrangement |
|
KMB Route Nos. 70K, 73, 73A and 278X |
Wah Ming / Sheung Shui bound |
Relocated about 25 metres westwards |
Appropriate traffic signs will be erected on site to guide motorists. Motorists are advised to follow the instructions on site and drive in utmost care. The bus company will display notices to advise passengers of the above temporary arrangement.