TRAFFIC ADVICE
Temporary Traffic Arrangements on Lin Cheung Road, Yau Ma Tei


       Motorists are advised that to facilitate the construction works for Central Kowloon Route, the following temporary traffic arrangements will be implemented in Yau Ma Tei from 0.00 am to 6.00 am daily from 4 to 6 December 2025:

  1. Lane Closure

The first, second and third left lane of Lin Cheung Road southbound near West Kowloon Bus Terminus will be temporarily closed to all vehicular traffic.

    2. Traffic Diversion


Affected vehicles from Lin Cheung Road southbound heading for Yau Ma Tei and Hung Hom will be temporarily diverted via Lin Cheung Road southbound, Lin Cheung Road northbound, Jordan Road westbound and Jordan Road eastbound.

        Appropriate traffic signs will be erected on site to guide motorists.